Property TypeUnit TypeAreaStarting PricePrice Breakup
1 BHKApartment425 - 482 Sq Ft. (Carpet Area)Ask For PriceClick Here
2 BHKApartment681 - 750 Sq Ft. (Carpet Area)Ask For PriceClick Here
3 BHKApartment1,047 Sq Ft. (Carpet Area)Ask For PriceClick Here

Presidence Eternia by Presidence Realty gives a systematic payment plan designed to make the house purchasing journey more easily and organised. The planned instalment method and affordable deposit payment can help purchasers divide their funds responsibility throughout of the purchase in place of handling a large amount at once. As well as with premier house and voguish lifestyle facilities, the development presents a choice for people considering property ownership in an known Mumbai neighbourhood. Its assemble of designed house, modern ease, and a connected place makes it an outstanding choice for both personal use and possibility enduring property value.

Exclusive Installments Payment Plan - (10/85/5)

InstallmentPayment (%)Milestone
Down Payment10%On date of issuance of Letter of Allotment
1st Installments10%On the date of execution of these present
2nd Installment5%On commencement of RCC work of 1st Floor Slab
3rd Installment5%On commencement of RCC work of 2nd Floor Slab
4th Installment5%On commencement of RCC work of 3rd Floor Slab
5th Installment5%On commencement of RCC work of 4th Floor Slab
6th Installment5%On commencement of RCC work of 5th Floor Slab
7th Installment5%On commencement of RCC work of 6th Floor Slab
8th Installment5%On commencement of RCC work of 7th Floor Slab
9th Installment5%On commencement of RCC work of 8th Floor Slab
10th Installment5%On commencement of RCC work of 9th Floor Slab
11th Installment5%On commencement of RCC work of 10th Floor Slab
12th Installment5%On commencement of RCC work of 11th Floor Slab
13th Installment5%On commencement of RCC work of 12th Floor Slab
14th Installment5%On commencement of RCC work of 13th Floor Slab
15th Installment5%On commencement of RCC work of 14th Floor Slab
16th Installment5%On commencement of RCC work of 15th Floor Slab
Final Installment5%On commencement of RCC work of 16th Floor Slab